The new church and school property location:
28750 N. North Valley Parkway, Phoenix, AZ 85085

 

December 11, 2018    APS working on the tie in                                Off site work

     

Overview                                                                                           Barricades and Night Work

     

November 15, 2018                                                                         APS Dig

    

November 15,  2018        Paving

    

Inside –    Cabinets going in

    

Week of November 12, 2018                   Parking lot progress and Fire line

                

November 2, 2018   More concrete                                                       New doors

          

Sinks going in                                                                                     Lights and flex hose

        

October 22, 2018  Progress on the concrete walkway.                         Tile going down.

    

October 21, 2018

September 27, 2018    Stucco progress

   

September 26,  2018     Stucco color going on

   

September 21-24,   2018     Stucco, first layers

    

September 19, 2018                 Curb Pour

   

September 14, 2018  Lath

   

September 13, 2018   Street work

    

September 12,  2018  Last exterior doorframe set.

       

Drywall and taping                                                                                                    Street – saw cutting

          

 

9-7-18 Drywall,  Taping and Grading

  

August 22, 2018  Drywall going in                                     August 24, 2018

  

August 21, 2018   Major progress on sheathing                     Fire line

 

August 16, 2018   Enclosing the parapet,                        Installing DensGlass sheathing

 

Halls, Walls, and Window openings                               Sunlight across the hallway

 

August 2, 2018  Soon there will be walls.

August 1, 2018 Ducts going in                                       August 2,  2018 roof taking shape

 

July 31, 2018  Back of building – installing insulation.

 

July 26, 2018                                                                           July 30, 2018

 

July 19, 2018 Preparing for new walls and roof

 

July 17, 2018     Awning going up

 

Bracing for Air Conditioning

 

July 11, 2018    The skeleton is complete

July 10, 2018

 

July 9, 2018

  

July 7, 2018

  

July 3,  2018 First Steel upright

 

Standing Steel at Standing Stones

 

June 27 Pouring Concrete                                                      and working all night

                     

Sunrise                                                                                                 Finishing touches

 

June 21, Rebar is taking shape.  109 degrees, these men are rocking it!       June 23,  Dry wells finished.

 

June 19 Underground utilities finished,  300 tons of aggregate base added,  and preparing to pour foundation.

  

June 12 Underground Utility Lines going in.

    

June 4,   Footings                                                                                              June 4,  Pouring Concrete

                                              

May 29    Rebar going in                                                                                 May 29, Digging 80 foot Dry Well

                                                   

April 3, 2018    Moving Dirt                                                                                May 21, 2018   Digging footings