April 3, 2018    Moving Dirt                                                                                May 21, 2018   Digging footings

                               

May 29    Rebar going in                                                                                 May 29, Digging 80 foot Dry Well

                                                   

June 4,   Footings                                                                                              June 4,  Pouring Concrete

                                              

June 12 Underground Utility Lines going in.

    

June 19 Underground utilities finished,  300 tons of aggregate base added,  and preparing to pour foundation.